Saturday, April 4, 2009

Lock it in ...

03.04.09 - As we received another invoice from our Builder I decided to visit the house early Friday morn. At a first glance, it seems nothing has changed outside ... but if you would look closely, the Upper part of the Bricks have been acid washed


A closer look at the Acid Washed Bricks


Weatherboards at the back has been installed


The Evaporative Cooling as well as the Heaters are also installed in the roof


The Permanent Front Door has been installed, with the glazed design though the colour is still not finalized


Going inside the house is a bit tricky now, as part of the inspection, we were accompanied by the the Site Super and had the chance to take some pictures inside the house. Plaster Boards on the 2nd Floor is almost complete.

The Master's Bedroom

The Spa in the Ensuite


The Activity Room


The Bath in the common toilet


The 1st Floor is still work in progress, you can see the insulation being placed between the frames and the Plaster Board


The Heating and Cooling Vents ...


The stairs will commence installation and targeted to be finished within 2 weeks ...


The scaffolding's are coming going down next week ... the Lock-up Stage is Complete, next Stop ... the Fixing Stage ...